Edition: abc5c37db6256889edecf814a809bcbe3dc326cb9c770f5fb2e3eab049e91802
---
id: OM.C01
kind: case
title: Release Recovery with Shared QA
version: 0.1.1
language: en
author: Anna Lubenchenko
license: CC-BY-4.0
license_url: https://creativecommons.org/licenses/by/4.0/
editorial_status: draft
distribution: public
intended_use: Follow a constructed operating question from raw records to a checked feasible sequence, a changed-condition decision and a receiving work product.
applicability:
- Verification, unattended build work and acceptance share consequential dependencies and resource windows.
- A schedule question can be answered under supplied deterministic assumptions without claiming a delivery probability.
source_refs:
- id: AOM-OPS-GUIDES-2026-11-26
description: Authored constructed teaching case; private design provenance is maintained outside the serving corpus.
relations:
- type: illustrates
target: OM.P15
note: Recover operations, product versions, real shared resources and receiving conditions.
- type: illustrates
target: OM.P05
note: Check a feasible sequence rather than treating a load total or one failed ordering as decisive.
- type: shows_boundary
target: OM.P06
note: A feasible deterministic schedule is not a delivery probability or an authorized promise.
- type: shows_boundary
target: OM.P07
note: A new exception needs an accounted-for displacement or another qualified provision.
validation_refs: []
---
# OM.C01 — Release Recovery with Shared QA
This is a constructed teaching case, not an enterprise observation, executed trial or hidden evaluation fixture. All times, durations, availability and receiving rules below are supplied assumptions. The question is whether the R2 candidate can complete the required acceptance by noon, while preserving an existing obligation. No estimated duration is silently converted into an observed event.
## Raw account
A manager says: “The release card is in QA again. QA must be our bottleneck. Put the release first and promise noon.” The tracker has one release card and a separate review card. The following evidence and planning premises are available:
| Item | Supplied record or premise |
|---|---|
| Candidate identity | R1 failed an interface check yesterday. R2 contains the correction. The relevant verification scope for R2 is already established; its 90 minutes includes the affected regression checks. Unaffected valid evidence remains usable under the supplied rule |
| Readiness | R2 and all verification inputs are available at 09:00. No additional preparation is required under these premises |
| Verification V | One qualified verifier Q is occupied continuously for 90 minutes; this operation must precede build B |
| Build B | A separate build service is reserved and able to run for 60 uninterrupted minutes after V. It requires no Q attention, setup, supervision or return during those 60 minutes under this case's explicit assumptions |
| Acceptance A | After successful B, Q and the authorized release owner must jointly review the matching result for 30 uninterrupted minutes. This prepares the accepted release candidate; deployment and operating effect are outside the present result |
| Other obligation O | Q owes a separate 60-minute uninterrupted review by noon. Its inputs are ready at 09:00; it has no dependency on R2 |
| Calendars | Q is available 09:00–12:00. The build service can run 09:00–12:00. The owner is available 11:30–12:00. There is no other qualified capacity in this baseline |
| Governing conditions | Both obligations must be preserved; no actor has authorized canceling O or bypassing verification/acceptance. Completion times are conditional on the supplied durations and successful outcomes |
The record supports yesterday's failed R1 check and a proposed R2 route. It does not establish that R2 has passed, that either result has been accepted or that Q limits the whole enterprise. If any premise is actually unknown, keep that premise unresolved instead of borrowing certainty from this teaching case.
## Reconstruct the consequential operations
Use [P15](../patterns/OM.P15-reconstruct-the-operating-arrangement.md) to separate the product versions, the performed R1 attempt and the planned R2 work. V → B → A is a dependency chain; O is independent except for sharing Q. Q is one resource, even if two team plans each list the person. The owner supplies an additional joint contribution, not a substitute verifier. A 60-minute build is elapsed processing time and service occupation, not 60 minutes of Q work under the stated premises.
Use [P03](../patterns/OM.P03-discriminate-the-operating-constraint.md) only for the question still open. “In QA again” leaves different explanations: an affected check legitimately repeats after a changed candidate, an earlier input was inadequate, or qualified provision is insufficient in a relevant window. The supplied facts settle the bounded scheduling question below; they do not settle the history's causal contribution or establish a universal staffing remedy. More data are unnecessary for this conditional schedule, but would be needed for those stronger claims.
## Construct and check an answer
Q demand is 90 + 60 + 30 = 180 minutes, exactly the three-hour window. That necessary load bound does not establish feasibility: precedence, uninterrupted duration and the owner's window still matter. [P05](../patterns/OM.P05-protect-shared-capacity-and-control-release.md) yields this witness:
| Interval | Q | Build service | Release owner |
|---|---|---|---|
| 09:00–10:30 | Verify R2 (V) | Not required | Not required |
| 10:30–11:30 | Other review (O) | Build R2 (B) | Not required |
| 11:30–12:00 | Joint acceptance review (A) | Finished | Joint acceptance review (A) |
The sequence preserves both obligations and fits every stated dependency and calendar. If O ran first at 09:00–10:00, V would finish at 11:30 and B at 12:30, after the owner's available window. That ordering fails; it does not prove the problem infeasible. Conversely, the witness does not establish robustness: there is no spare Q time, and the critical sequence reaches noon exactly. Failure, extra setup or longer actual duration can invalidate it.
The supported conclusion is: “There is a feasible sequence under the supplied conditions. Reserve and authorize it under the applicable arrangement, retain the affected verification and matching acceptance, and expose its lack of time margin.” [P06](../patterns/OM.P06-reconcile-scope-forecast-and-promise.md) prevents converting that conclusion into a confidence percentage or a promise made by an unauthorized agent. If the governing arrangement has already allocated these slots and authorized this commitment, reuse that evidence rather than demanding duplicate approval.
## A changed condition changes the decision
At 08:50 an additional protected incident check is reported. It requires 30 minutes of Q before noon and cannot be combined with any existing operation. Now Q demand is 210 minutes against 180 available. This is a violated necessary bound for preserving all four operations in that window, not a failed heuristic. Reordering alone cannot repair the 30-minute shortfall.
Use [P07](../patterns/OM.P07-admit-an-expedite-and-account-for-displacement.md) to apply any existing immediate-protection rule and reconcile the affected obligations. A proposal to defer O must name the responsible authority, the receiving consequence and the actual new slot; it does not itself release O's obligation. Additional qualified provision helps only if it can perform the relevant operation with the necessary access and receiving conditions. A changed release promise needs the applicable decision. Do not invent an overtime budget or remove required acceptance to make the arithmetic fit.
If actual protection is already authorized, do not delay it for an ordinary backlog ceremony. Account for its work and resulting displacement under that rule. If a pre-existing estimate already included this check, the additional-demand premise would be false: reconcile the occurrence instead of adding it again.
## Work product and follow-through
Return a short decision note with the exact candidate/result, the premises, the checked baseline schedule, the changed-condition shortfall, any still-conditional alternative and the responsible receiving decision. The scheduler receives a proposed allocation; the commitment owner receives the effect on accepted obligations. Neither receipt proves that the schedule was executed.
During execution retain actual start/finish and failure events, candidate identity and the applicable acceptance evidence. A delay or failed check is interpreted through [P18](../patterns/OM.P18-interpret-operating-signals-and-choose-a-response.md): protect the required result, distinguish the acceptance rule from a process-monitoring signal, and investigate only what remains decision-relevant. One miss does not prove a change in the process or justify changing a monitoring model.
After the work, close only the claim the evidence supports: a performed check, a successfully built candidate or acceptance under the specified rule. Deployment, receiving use and operating effect require their own evidence. Freed attention during an unattended build is a scheduling possibility; it is not automatically a cash saving or additional accepted output.
## Attribution and source scope
Authored AOM text: Anna Lubenchenko, [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/). Source contributions and limits are identified in the [public bibliography](../../bibliography.md).
Content SHA-256: 21eb91aa6fb6e08dc7c766a6f911d829e7c3af6865f12040be4c9b7ef9a7019b