title: Portfolio Build, Run and Protected Capacity
version: 0.1.1
language: en
author: Anna Lubenchenko
license: CC-BY-4.0
license_url: https://creativecommons.org/licenses/by/4.0/
updated: 2026-11-27
editorial_status: draft
distribution: public
intended_use: Follow a post-launch service obligation through future workload, a capacity bound, a qualified handoff and checked alternative schedules.
applicability:
- New delivery creates continuing demand on the same specialist needed by accepted future build work.
- A proposed handoff or additional contributor changes both transition and continuing resource requirements.
source_refs:
- id: AOM-SEVEN-BOOKS-2026-11-26
description: Authored constructed teaching case from qualified TameFlow/CIO findings; every quantity, window, capability and policy here is a supplied scenario assumption, not enterprise evidence.
- id: FPF-OPS19-423f9d3
url: https://github.com/ailev/FPF/blob/423f9d3fef92bafec7b092b910e8ce056a0f607d/DPFs/Management%20DPF%20Suite/OPERATIONS-MANAGEMENT-PRINCIPLES-FRAMEWORK.md?plain=1#L6056-L6292
relations:
- type: illustrates
target: OM.M03
note: The same specialist's future service and build claims must share one calendar even before the build item arrives in its ready queue.
- type: illustrates
target: OM.M11
note: Post-launch run demand and the work needed to transfer it can consume the same scarce provision.
- type: illustrates
target: OM.P19
note: Reconcile the accepted build result, continuing service, protection and future handoff under distinct authorities.
- type: illustrates
target: OM.P05
note: Check explicit schedules after the necessary load bound; preserve review and acceptance joins.
validation_refs: []
---
# OM.C03 — Portfolio Build, Run and Protected Capacity
This is a constructed teaching case, not an enterprise observation, performed trial or hidden evaluation fixture. All quantities, methods, windows, capabilities and authority conditions below are hypothetical inputs. An estimated or scheduled hour is not reported as an observed hour. The case asks what remains feasible after a release adds continuing service work to the same expert who owes the next build result.
## The account received by the manager
The portfolio owner says: “The launch succeeded. The expert still has a twenty-hour build allocation, and the new package needs eighteen hours. Start it on Monday.” The build queue is empty at the Friday planning cutoff; package Q's prepared input will be available Monday at 13:00 under the supplied scenario. Q is already committed for acceptance by the following Friday at 16:00.
The other supplied facts are:
| Item | Current scenario premise |
|---|---|
| Expert E | Forty usable hours, Monday–Friday 09:00–17:00; ordinary breaks and human conditions are already accounted for in these declared eligible windows |
| Existing run service | Sixteen E-hours: Monday 09:00–13:00 and Tuesday–Friday 09:00–12:00 |
| Protected reserve | Tuesday–Friday 16:00–17:00, four E-hours in total, unavailable to discretionary build or training under the supplied rule; its protected response is feasible in these windows |
| Previous build availability | Monday 13:00–17:00 and Tuesday–Friday 12:00–16:00: twenty E-hours |
| Package Q | Seventeen E-hours of engineering, validly interruptible at the stated block boundaries with no extra setup under the supplied method, followed by one hour of joint acceptance with receiver O |
| Acceptance | O is available Friday 15:00–16:00; all other acceptance inputs and permissions are supplied; earlier independent completion of a child does not replace this event |
| New run obligation after launch | Six additional recurring E-hours: Tuesday, Wednesday and Thursday 12:00–14:00; it is distinct from the existing sixteen hours and must continue from this week |
| Authority | Existing and new run service, reserve and Q's accepted terms remain in force. The portfolio owner cannot unilaterally cancel them. Relevant holders can consider a qualified handoff or a revised agreement; neither is already performed |
The forty-hour total is an effective calendar assumption for this teaching example, not a universal working-week or utilization target. The four-hour reserve is supplied by this scenario's policy, not recommended as ten percent for other operations. No overtime or absent qualified substitute is added implicitly.
## First correction: the new launch changes the next week's demand
Q is not yet ready at the cutoff, but its future claim is already material. The empty ready queue says nothing about that obligation. [OM.M03](../models/OM.M03-shared-capacity-active-work-and-waiting.md) keeps actual ready work separate from prospective demand. The new service occupies windows formerly available for Q:
`40 usable − 16 existing run − 6 new run − 4 protected = 14 build hours`.
Q requires eighteen E-hours including final acceptance. Under the unchanged week, service and protection, the shortfall is four hours. This violated necessary bound rules out completing all the stated work with E alone; another ordering cannot add the missing hours. It establishes neither a permanent enterprise bottleneck nor an optimal hiring decision.
Without the new run duty, a baseline sequence would have been possible. Engineering occupies Monday 13:00–17:00, Tuesday–Thursday 12:00–16:00, and Friday 12:00–13:00, totaling seventeen hours. Joint acceptance uses Friday 15:00–16:00. Friday 13:00–15:00 remains unallocated. The new run duty consumes six of those previously available build hours, so the original allocation no longer supplies the result.
The [P19](../patterns/OM.P19-reconcile-portfolio-starts-buffers-and-operating-commitments.md) question is how to preserve continuing service, protection and the recipient's obligation through an actual alternative. Raising Q's priority, filling the ready queue or changing its internal forecast date does not resolve that question.
## Alternative A: prepare a supported handoff
A proposed contributor R could take the six-hour run duty after qualification. The supplied transition method requires four hours of joint E–R training and a supervised qualification exercise; all assessment work is included in those four hours under this example's supplied method. Its result must establish R's competence for this scope, and access must also be current. Training attendance alone does not establish a successful qualification result. Until qualification and the receiving arrangement are established, E retains the new run work.
The training can use Monday 13:00–15:00 and Friday 12:00–14:00. R has matching independent windows. Those four E-hours are additional training and are not included in either run estimate. During this transition week the necessary bound becomes:
`40 − 16 existing run − 6 new run − 4 reserve − 4 training = 10 build hours`.
The transition therefore cannot preserve Q's original deadline with E alone. Starting training may be a reasonable future-capability choice, but requires an actual disposition for Q and any other affected work. A possible agreement to accept Q next week is a proposal until the relevant holder and recipient establish it. If they cannot revise the promise, this handoff branch remains insufficient for the present obligation; another current remedy is still needed.
Suppose that the qualification result, access and receiving responsibility are subsequently established for R, and that Q is validly moved to an otherwise identically provisioned later week. In this changed scenario R performs the new run duty Tuesday–Thursday 12:00–14:00. The supported method also retains two hours of joint E–R review each week, Tuesday and Wednesday 14:00–15:00. R has all eight required hours, without displacing another service. This review is additional to R's six service hours and is counted on both calendars.
E then has `40 − 16 − 4 − 2 = 18` build hours. The following sequence demonstrates feasibility under the changed terms:
| Day | E engineering for Q | E–R review | R's new run service | E protected reserve |
|---|---|---|---|---|
| Monday | 13:00–17:00, 4 hours | None | None | None |
| Tuesday | 12:00–14:00 and 15:00–16:00, 3 hours | 14:00–15:00 | 12:00–14:00 | 16:00–17:00 |
| Wednesday | 12:00–14:00 and 15:00–16:00, 3 hours | 14:00–15:00 | 12:00–14:00 | 16:00–17:00 |
| Thursday | 12:00–16:00, 4 hours | None | 12:00–14:00 | 16:00–17:00 |
| Friday | 12:00–15:00, 3 hours | None | None | 16:00–17:00 |
Existing run service retains its original morning windows. Engineering totals `4 + 3 + 3 + 4 + 3 = 17` E-hours. Q's joint E–O acceptance follows Friday 15:00–16:00, giving eighteen build/acceptance hours. R's service and review do not overlap. Every retained E reservation fits the calendar.
This is a feasible continuing arrangement for the supplied later week. It is not evidence that qualification occurred, that Q was accepted, or that the original promise was repaired on time. There is no additional unallocated E time beyond the specified protection. A new E task or longer review reopens this schedule; protected reserve cannot be silently reused to absorb it.
## Alternative B: independent qualified provision is already available
Change one premise: R already has supported competence, access and accepted responsibility for the six-hour run duty, with the Tuesday–Thursday 12:00–14:00 windows independently available. The method requires no E training, review or continuing supervision for this scope. The service holder can make the handoff effective before Tuesday under the existing rule.
Under these explicit conditions the new run duty consumes R's provision rather than E's. E retains the baseline twenty-hour build availability, and the baseline seventeen-hour engineering sequence plus Friday 15:00–16:00 acceptance fits the original week. This is a positive supported option. It must not be rejected merely because a previous handoff scenario required training.
Check R's donor obligations before relying on independence. If R must perform another protected task in those same windows, the premise fails. If only a name or training plan is supplied, competence and availability remain unresolved. Conversely, adequate current evidence permits reuse without another ceremonial training programme.
## Alternatives that do not yet settle the choice
Borrowing four protected hours is excluded by the supplied reserve rule. An authorized change to that rule would require its own protection basis; an empty incident log does not provide one. Dropping four hours of Q has no supported acceptance basis in this case. A smaller independently useful result could be compared only if its actual scope and terms are established. Buying additional provision is conditional on qualified availability, price, funding, access and the window it supplies.
The schedules establish feasibility under assumptions, not economic preference. Compensation, purchases, demand, transition expense and payment dates have not been supplied. [OM.P09](../patterns/OM.P09-compare-service-and-fallback-options.md) would compare them if they can change the decision. Salaried hours released for build are not automatically a cash saving, and a resource-hour ranking does not waive Q's promise.
## A changed acceptance or support condition reopens the result
If O's only acceptance window moves to Friday 12:00–13:00, the handoff schedule above no longer demonstrates feasibility. Before Friday it has completed fourteen engineering hours; the three remaining engineering hours cannot precede that window under the supplied calendars. Inspect another qualified sequence or an authorized acceptance change. The favorable weekly total of eighteen is insufficient.
If the new launch instead retires an old six-hour service duty using the same required windows and no additional transition, its net E demand may be zero. Reconcile the actual removed duty and current obligations; do not add six merely because a release occurred. If new support is merely forecast and not yet observed, retain that scenario status and the uptake condition in any commitment based on it.
## Receiving product and follow-through
Return the scoped conflict, the four-hour original deficit, the transition's ten-hour build limit, the later qualified-handoff witness, and the independently qualified current alternative. Name each missing qualification, handoff or promise decision and what may already proceed under current authority. The service holder receives the handoff proposal; the commitment holder receives the changed outlook and remedy options; the resource owner receives the actual schedules and protected windows.
If authorized action follows, verify qualification, accepted responsibility, changed terms where required, actual work and matching acceptance separately. Preserve the original promise for later assessment. An operational launch, a handoff decision and fulfillment of Q are different events. Repeat this review only when a consequential premise changes.
The [public bibliography](../../bibliography.md#seven-book-sources) identifies the TameFlow/CIO contributions: prospective workload, build-to-run demand and protection. OPS.19 supplies cross-case reconciliation under actual authority; the case adapts those contributions under its supplied assumptions. The arithmetic and schedules are authored examples for M03/M11/P05/P19, not empirical evidence for their effectiveness. All variants are open development material and must remain outside an independent held-out set.
## Attribution and source scope
Authored AOM text: Anna Lubenchenko, [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/). Source contributions and limits are identified in the [public bibliography](../../bibliography.md). FPF sources are by Anatoly Levenchuk, FPF Library, under CC BY 4.0. This AOM adaptation adds operating instructions, explanations and constructed examples under the stated limits; it does not reproduce or implement every source method.