title: Shared Capacity, Active Work and Waiting
version: 0.1.2
language: en
author: Anna Lubenchenko
license: CC-BY-4.0
license_url: https://creativecommons.org/licenses/by/4.0/
updated: 2026-11-27
editorial_status: draft
distribution: public
intended_use: Explain how several work demands compete for the same qualified provision and distinguish actual occupation, reserved availability, waiting and future demand.
applicability:
- A plan treats several functions, stations or projects as independently resourced although they use the same people, equipment or windows.
- Visible queues or elapsed status durations are being used to infer resource use, future availability or a capacity deficit.
source_refs:
- id: AOM-SEVEN-BOOKS-2026-11-26
description: Authored application informed by the cited seven-book sources; public editions, bounded contributions and transfer limits are identified in the bibliography.
- id: TENDON-TAMEFLOW-2022
description: Steve Tendon, The Book of TameFlow, edition 17 January 2022; chapters 3–4, 6, 8 and 14, especially pp. 127–131 and 226–230.
- id: CIO-TAMEFLOW-2014
description: The CIO's Guide to Breakthrough Project Portfolio Performance, supplied 2014 edition; chapter 2, When IT Is the System Constraint. Qualified full-reading findings identify the build-to-run demand mechanism; no book gain or universal ratio is adopted.
- id: FPF-OPS19-423f9d3
url: https://github.com/ailev/FPF/blob/423f9d3fef92bafec7b092b910e8ce056a0f607d/DPFs/Management%20DPF%20Suite/OPERATIONS-MANAGEMENT-PRINCIPLES-FRAMEWORK.md?plain=1#L6056-L6292
relations:
- type: explains
target: OM.P05
note: Explains why shared-resource competition requires actual common windows. Pass consequential operations, resource identities, occupied intervals and current windows when a start or sequence needs a feasibility check; preserve unknown duration and protected availability.
- type: explains
target: OM.P19
note: Explains how future demand and conflicting current uses can make local decisions incompatible across cases or horizons. Pass that identified conflict when consequential; one sufficient local schedule can remain with P05.
- type: shows_boundary
target: OM.M11
note: A present resource conflict does not establish a continuing dependence loop; that claim also needs the capability-change route and later receiving conditions.
validation_refs: []
---
# OM.M03 — Shared Capacity, Active Work and Waiting
Use this model when a queue owner or service owner needs to explain why apparently sufficient resources do not support the required result. One specialist may prepare requirements, review code, respond to incidents and support deployed services. Naming those functions in different plans does not give each plan another specialist. Conversely, a task waiting for an external input need not occupy that specialist throughout its recorded duration.
This is an authored model draft. Its constructed examples explain conditional mechanisms; they do not establish a diagnosis of an enterprise, an effective staffing rule or a measured intervention effect.
## Boundary and quantities
Identify the accepted result, work population, actual resources and calendar interval before comparing demand and capacity. Keep the recipient's original waiting origin even when an internal admission boundary changes.
| Quantity | Interpretation needed for the decision |
|---|---|
| Active occupation | The person's attention or equipment use required by a particular operation, including consequential setup, review and return work |
| Reserved availability | A window held for a named service or protection under actual terms; it can be unavailable to other work without continuous activity |
| Autonomous processing | An operation occupies its equipment or service while requiring only specified loading, supervision or return contributions from a person |
| Elapsed waiting | Time before a needed input, resource, permission or acceptance becomes available; it does not establish continuous labor |
| Remaining demand | Work still required for the selected result, including future route visits and returns under stated assumptions |
| Usable capacity | Qualified provision available in actual windows, with access, joint participation and independent protections retained |
Person-hours, pair-hours, machine-hours and calendar days describe different quantities. Two people required together provide a joint window for that operation. A free calendar without the necessary competence or access does not provide usable capacity.
## Mechanism
The candidate mechanism is:
> Several works claim the same qualified provision → their necessary occupied or reserved windows conflict → some work cannot start or finish under the original arrangement → waiting, displacement or a revised commitment follows.
Repeated switching can add setup, lost context or revalidation to that demand. Those additional costs require evidence or an explicit scenario assumption. A card moving between columns does not measure them. Likewise, reducing an item's waiting time does not automatically release an equal number of person-hours. Reducing internal WIP can move waiting before admission while accepted output and the recipient's elapsed wait remain unchanged.
A sum of required hours greater than usable hours establishes a deficit under the stated assumptions. A sum that fits does not establish a feasible sequence: uninterrupted spans, predecessor readiness, joint work, operator returns and downstream acceptance can still exclude the result. [OM.P05](../patterns/OM.P05-protect-shared-capacity-and-control-release.md) constructs and checks the sequence when the question needs one.
## Future workload is distinct from the current queue
A resource can have an empty ready queue today and face substantial future demand from work already admitted upstream. A virtual workload account makes those known future visits visible before another start claims the same windows. It is a prospective representation, not evidence that the work has arrived, is ready or has been performed.
For each consequential package retain its commitment status, required remaining operation, actual resource or qualified pool, readiness/dependency, duration basis, requested window and acceptance join. Keep optional candidates separate from accepted obligations. Do not count the same remaining work both in its parent estimate and in a child operation. A recurring service demand is represented for the relevant future periods, not added once and then forgotten.
Compare load within each resource and window. Count-based queues may suffice for a sufficiently similar mix; a mixed queue needs a supported workload basis. Dividing unlike items by an old average throughput does not establish comparable clearance time. The longest future queue is a candidate for investigation, not proof of the operating constraint or a feasible schedule. A late prerequisite, parallel processing positions or a different acceptance window can change that conclusion.
After a successful release, support, monitoring, compatibility and recovery can require continuing attention from the same people who build the next release. Recover whether that work is new, its uptake and frequency, its duration basis and who will actually perform it. The build-to-run contribution is conditional: a release may replace old work, require negligible additional support or use independent qualified provision. [OM.M11](OM.M11-scarce-expertise-and-deferred-capability-work.md) explains the additional loop when improving that provision needs the same scarce specialists.
## Discriminate the explanation
| Live explanation | Evidence or calculation that can change the response |
|---|---|
| Ready demand exceeds usable qualified windows | Pair required operations and ready times with actual calendars, reservations and occupation; check a necessary bound and, where relevant, the sequence |
| The work is waiting for an input rather than a person | Establish the input's availability and whether the person could act in the supposedly lost window |
| An automated run has been counted as continuous human work | Recover the actual loading, supervision and return requirements alongside the machine's occupation |
| Apparent missing demand is already included | Reconcile the operation with parent estimates, support allowance and other records; expose its contribution without adding it again |
| A later queue is hidden by a local view | Trace already accepted upstream work to future resource visits and receiving windows |
| New run obligations reduce build availability | Compare dated continuing service demand before and after release, including displaced or retired service, rather than inferring load from release count |
Use existing adequate evidence. If the decisive input is unavailable, return the exact unresolved resource, duration or readiness question. An unavailable record does not establish idle time or absent work.
## Constructed case: waiting and future demand
Q has six qualified hours before a required acceptance window. A ready review needs two Q-hours. An already committed package upstream will become ready in time and needs three Q-hours, including its acceptance work. A proposed new review needs two more Q-hours. No substitute or additional usable window exists in this scenario.
Looking only at the ready queue suggests four hours remain after the first review. Accounting for the committed future visit gives `2 + 3 + 2 = 7` Q-hours against six. The proposed combination is infeasible under these conditions. This does not identify how the commitment owner should revise scope or order; it supplies the missing resource consequence.
**Changed condition:** another qualified reviewer with independent time, access and acceptance authority can perform the proposed two-hour review without Q preparation or oversight. That demand no longer competes for Q. Check the separate reviewer's route and window; do not preserve the earlier deficit merely because the card has the same title.
**Counterexample:** an upstream item spends three days waiting for customer data but needs only a half-hour Q review after receipt. Counting the three days as Q labor is unsupported. If the input arrives after the only acceptance window, adding Q hours still does not make that result timely.
## Action, burden and receiving product
Possible responses include protecting a real window, changing start order, preparing the missing input, using qualified independent provision, reducing avoidable return work, or revising a promise under its authority. Each response needs a mechanism connecting the changed condition to the accepted result. Hiring, automating or delegating by name alone supplies none of the missing contributions.
Return a compact account of **result/window → actual resource → current and future demand → readiness and occupation basis → protected availability → supported bound or unresolved relation → feasible response to check**. [OM.P11](../patterns/OM.P11-discover-and-account-for-invisible-work.md) can repair omitted work; [OM.P15](../patterns/OM.P15-reconstruct-the-operating-arrangement.md) can recover a missing route. Use only the unresolved contribution. Cross-case conflicts that also affect continuing service or future capability go to [OM.P19](../patterns/OM.P19-reconcile-portfolio-starts-buffers-and-operating-commitments.md).
Observation and schedule maintenance consume provision too. Stop at the resolution needed for the current decision, preserve sufficient unchanged accounts, and reopen affected claims after changed mix, readiness, resource identity, qualification, calendar, return behavior or service obligation. A corrected plan establishes a better account; it does not establish that the operation has changed.
## Grounds and evaluation limits
TameFlow contributes the future-workload perspective and the distinction between productive, protective and excess capacity. Its illustrative gains, universal constraint claims and equation of item waiting with reclaimed effort are not adopted. The CIO guide contributes the conditional accumulation of operating demand after release. The [public bibliography](../../bibliography.md#seven-book-sources) identifies the editions, contributions and transfer limits.
OPS.19 by Anatoly Levenchuk supplies preservation of distinct work, measures, horizons and protection conditions in a cross-case decision. Its complete body was read through MCP FPF Tools at snapshot `20261125T054841Z-7b084255babf17c2`, source commit `423f9d3fef92bafec7b092b910e8ce056a0f607d`; see the pinned source and [licensing notice](https://github.com/ailev/FPF/blob/423f9d3fef92bafec7b092b910e8ce056a0f607d/LICENSING.md). This model is an authored application, not an implementation of every dependency.
Development cases must distinguish continuous occupation from waiting, joint from independent provision, future demand from ready work, and an actual deficit from a failed ordering. The [portfolio case C03](../cases/OM.C03-portfolio-starts-and-operating-load.md) develops the post-launch branch. These are teaching and evaluation requirements; no passing agent or field result is asserted.
## Attribution and source scope
Authored AOM text: Anna Lubenchenko, [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/). Source contributions and limits are identified in the [public bibliography](../../bibliography.md). FPF sources are by Anatoly Levenchuk, FPF Library, under CC BY 4.0. This AOM adaptation adds operating instructions, explanations and constructed examples under the stated limits; it does not reproduce or implement every source method.