intended_use: Produce a reproducible forecast or bounded scenario for the required result and connect it to an authorized service decision.
applicability:
- A proposed date or scope needs support from remaining work, calendars and a suitable history or scenario.
- An existing promise is at risk because its scope, dependencies, available resources or forecasting basis changed.
source_refs:
- id: AOM-OPS-GUIDES-2026-11-26
description: Internal authored synthesis of qualified guide findings; examples and calculations are constructed.
- id: FPF-OPS13-423f9d3
url: https://github.com/ailev/FPF/blob/423f9d3fef92bafec7b092b910e8ce056a0f607d/DPFs/Management%20DPF%20Suite/OPERATIONS-MANAGEMENT-PRINCIPLES-FRAMEWORK.md?plain=1#L4413-L4639
description: Operations Management Principles Framework, 27 October 2026 edition; OPS.13, especially sections 4.1–4.5.
- id: Vacanti-Seele-FlowMetrics-2022
description: Daniel Vacanti and Will Seele, Flow Metrics for Scrum Teams, Leanpub edition dated 10 August 2022; Chapter 5 Sprint Planning, Part I, MCS in Sprint Planning; Chapter 7 The Daily Scrum, SLE and age checkpoints.
- id: Vacanti-WhenWillItBeDone-2018
description: Daniel S. Vacanti, When Will It Be Done?, supplied edition dated 29 July 2018; Chapter 6, input selection, calendar and model assumptions. The exact examples below are constructed, not reproduced book data.
relations:
- type: requires_result
target: OM.P05
note: Use a feasible resource sequence or impossibility bound when aggregate history cannot answer the scope question.
condition: "The forecast or bounded scenario depends on an unresolved feasible resource sequence or impossibility bound."
result: "A supported sequence or necessary bound for the actual remaining scope and qualified calendars."
reuse_or_stop: "Reuse a sufficient current arrangement; a deterministic feasibility result supplies no delivery probability by itself."
- type: requires_result
target: OM.P07
note: Account for changed priorities, displacement and protected response before relying on the revised outlook.
condition: "The outlook depends on an unresolved urgency decision, displacement or protected response."
result: "The effective priority disposition and accounted-for displaced work, recovery and protected response."
reuse_or_stop: "Reuse an effective current disposition; preserve independently authorized protection and do not require a new approval already supplied by the rule."
- type: requires_result
target: OM.P15
note: Reconstruct the required bundle and acceptance route only where necessary.
condition: "Forecasting the required result depends on an unresolved bundle, dependency or acceptance route."
result: "A sufficient account of the required bundle, consequential operations and receiving completion conditions."
reuse_or_stop: "Reuse the current adequate route and scope; stop reconstruction when the forecast-relevant inputs are established."
validation_refs: []
---
# OM.P06 — Reconcile Scope, Forecast and Promise
This is an authored draft for AI Operations Manager. The example is synthetic and checks the calculation, not the accuracy of a real service forecast. Editorial review does not establish agent performance, independent practitioner validation or field effectiveness. It is available as a public source draft; this does not establish admission as validated runtime guidance.
## Use this when
A service owner or recipient needs to know what can be offered by a date, when a specified result may be available, or which existing promise needs attention. Return the supported forecast or scenario, its scope and uncertainty, and a concrete service disposition or decision proposal.
Keep three statements separate. A target says what the parties want. A forecast estimates an outcome under a model and conditions. A commitment records what authorized parties undertake for a recipient under the governing terms. A tracker date or a model percentile supplies neither agreement nor authority.
## Minimum inputs and capability
- The required result and acceptance event, recipient, current promise/target, relevant calendar, as-of time and required decision. Name any mandatory specific items, integration, external approval and final acceptance.
- The remaining scope, including open work and returns, counted once under a stated rule. Do not infer a complete bundle from a count of unrelated completed items.
- Applicable event records with stable IDs, event time and meaning, configuration/scope, corrections and coverage. A throughput series needs reliable completion events and calendar coverage; missing start times alone do not invalidate it, though they limit duration and age analysis.
- Actual work mix, readiness, resource/capability windows, priority policy, return behavior and material changes from the historical regime. Obtain the missing calendar or confirmation from its responsible source.
- A practitioner able to reconstruct the series and execute/check the selected calculation, with access and time for it. Obtain statistical or domain capability where the requested claim exceeds the simple method below.
- The authority for scope, resource and promise changes, affected obligations and the applicable risk/service requirement. Do not choose a risk tolerance on the recipient's behalf.
## Procedure
1. **Define the forecasted outcome and remaining scope.** Choose “at least N accepted units by H,” “date when all specified required items are accepted,” or another exact receiving question. Keep local completion, acceptance and availability separate where they occur at different boundaries. Preserve the original obligation until a valid revision takes effect.
2. **Check a sufficient bound or existing arrangement first.** If known work cannot fit the usable windows, return that result before simulating. If a small deterministic sequence and stated adverse case answer the question, use [OM.P05](OM.P05-protect-shared-capacity-and-control-release.md). A probabilistic model is required only for a probabilistic claim; a feasible scenario supplies no probability by itself.
3. **Convert events to a complete daily series.** Deduplicate the chosen accepted-result event by the declared unit/version rule; retain cancellations, returns and corrections separately. Enumerate every date in the selected calendar and count eligible acceptances on it. Assign zero only when event coverage establishes no eligible acceptance. Mark an unobserved date unknown; repair coverage, choose a justified different window or model its uncertainty explicitly. Never silently drop it or replace it with zero.
4. **Qualify the population and calendar for reuse.** Explain why the historical completion rule, work mix, demand, staffing, support and priority regime are applicable. Include real zero days, holidays and shutdowns according to the selected clock. A business-day series is mapped to the actual future business calendar; a calendar-day series retains weekends. Preserve known future outages. Examine batching and dependent runs of low/high output before selecting independent daily sampling. If dependence or a changed regime matters, use a justified block/scenario model or return a conditional scenario with the gap visible.
5. **Choose a model that can answer this scope.** Daily throughput resampling can answer an aggregate volume question when its exchangeability and continuing-demand assumptions are usable. It does not establish that particular blocked or dependent items will finish. For a mandatory bundle, use direct comparable bundle history or represent its identities, dependencies, remaining work and joint acceptance. Preserve known readiness constraints even when the historical average is favourable.
6. **Calculate reproducibly.** Retain the normalized series, calendar, data window/as-of, scope, sampling unit, dependence assumptions, horizon, implementation, and results. For simulation also retain seed, number of draws, quantile convention and any unfinished paths at the horizon. For fixed horizon H, calculate the mass `P(K >= k)` for “at least k.” For fixed N, use the first period cumulative output reaches N. A high percentile of output is not a high-confidence minimum output. Do not discard trials that have not completed or report them as finishing at the horizon.
7. **Check prediction quality within available evidence.** At historical cutoffs use only information then available, forecast the later interval and compare with its observed outcome under the same acceptance/calendar rule. Report the number and horizons of checks, misses, coverage limits and regime differences. If the model/window was chosen using those outcomes, they are development evidence; use separate later windows before claiming independent calibration. Overlapping windows are not independent replications. More simulation draws reduce simulation error, not historical uncertainty or model bias.
8. **Inspect aging work where it changes the result.** Show still-open items and their waiting origin, relevant age, known blocker and next available response. A percentile of completed durations is not an unchanged probability for an item already older than much of that sample. Do not subtract age from an old service expectation and retain its claimed probability. Choose an adequate conditional model or a bounded case review; old age alone does not authorize an expedite.
9. **Prepare or make the service decision under its authority.** Present feasible options: preserve, narrow, move the date, supply an available resource, refuse the new request or resolve a specific missing result. Include effects on existing recipients and required conditions/actions. If the holder already has authority under standing terms, no new ceremonial approval is required. If agreement is required, the forecast and recommendation remain proposals until that agreement is established; an internal replan does not release the earlier obligation.
10. **Set an actionable review condition.** Work backward from the last useful response time, including detection, routing/decision, resource availability and recovery/acceptance. Recompute only affected forecasts when the basis changes. If no remaining response can preserve the promise, return that consequence and supported alternatives now instead of scheduling a review after the useful window.
## Return and sufficient short path
Give the decision holder **required scope and accepted-result boundary → current terms → source series or bounded schedule → calculation and model conditions → forecast/scenario and calibration limits → feasible service options → authorized disposition or outstanding decision → review condition**. The data and settings can be an attachment to the existing service record; a new reporting system is optional.
For a known small job fitting an already supported service arrangement, confirm its scope, slot and governing terms and stop. For insufficient data, a supported deterministic alternative or explicit unresolved answer is a complete result for the bounded inquiry. “Unknown” is preferable to a fabricated probability.
## Constructed example: events to an exact resampling calculation
The illustrative service counts independently accepted work products under one completion rule. The event extract is complete for four business days; records for unsuccessful attempts are retained but do not count as accepted output. The toy model assumes the same regime, enough ready eligible demand, no material serial dependence and no future outage. Four observations do not establish those assumptions or predictive calibration for a real team.
| Business date | Eligible acceptance events | Coverage | Daily count |
|---|---|---|---:|
| Monday, 23 November 2026 | None | Complete | 0 |
| Tuesday, 24 November 2026 | A accepted | Complete | 1 |
| Wednesday, 25 November 2026 | B accepted; C accepted | Complete | 2 |
| Thursday, 26 November 2026 | D accepted | Complete | 1 |
As of the end of Thursday, the normalized series is `[0, 1, 2, 1]`. Friday 27 November and Monday 30 November are the next two business days in this example; Saturday and Sunday are excluded by the declared calendar, not deleted after seeing their output. The question is whether the continuing service can accept at least two eligible products, not whether a particular unresolved bundle will be ready.
Sample each observed daily value with equal weight and replacement. For this tiny example, enumerate every ordered sample instead of using random draws; this removes simulation error while leaving model uncertainty intact:
```python
from collections import Counter
from itertools import product
history = [0, 1, 2, 1] # repeated 1 preserves its observed weight
for horizon in (2, 3):
counts = Counter(sum(path) for path in product(history, repeat=horizon))
total = len(history) ** horizon
at_least_two = sum(n for k, n in counts.items() if k >= 2)
print(horizon, dict(sorted(counts.items())), at_least_two, total)
```
At two days the total-output counts for `K = 0, 1, 2, 3, 4` are `1, 4, 6, 4, 1`, among 16 equally weighted paths. Thus the toy-model mass for at least two is `11/16 = 68.75%`, and for at least one is `15/16 = 93.75%`. At three business days, ending Tuesday 1 December, at least two occurs in `57/64 = 89.0625%` of paths. These are exact consequences of the stated resampling model, not measured probabilities of the real future.
The service owner receives this illustrative calculation with its weak historical basis and can request a more defensible history/model or use an independently supported resource scenario. It supplies no actual customer commitment. In a real case, an authorized holder would compare the supported options with the service terms and consequences, then agree the chosen scope/date and conditions through the existing commitment relation.
**Changed condition — unknown coverage:** if Monday's extract is missing, its count is unknown. The four-value calculation is no longer supported. If Monday is merely removed, `[1, 2, 1]` gives a two-day total of at least two in every resampling path, illustrating the distortion; that conditional model is not evidence that the omitted day had positive output.
**Counterexample — mandatory bundle:** X and Y must both be integrated and accepted together. X's external input cannot arrive before Tuesday and the only final acceptance window is Wednesday. Two unrelated acceptances by Monday do not fulfill this bundle. Return the Wednesday-or-later bound under those conditions, then construct the remaining route; do not attach the aggregate 68.75% or 89.0625% to it.
## Constructed example: a known calendar and a selected sampler
A second toy service has complete accepted-output observations for one selected calendar week. The counts refer to the same accepted-result rule and include genuine zero days:
| Date | Weekday | Accepted count |
|---|---|---:|
| 16 November 2026 | Monday | 2 |
| 17 November 2026 | Tuesday | 2 |
| 18 November 2026 | Wednesday | 2 |
| 19 November 2026 | Thursday | 2 |
| 20 November 2026 | Friday | 2 |
| 21 November 2026 | Saturday | 0 |
| 22 November 2026 | Sunday | 0 |
The receiving question concerns at least one accepted result during the specified future dates, Saturday 28 and Sunday 29 November. The supplied calendar establishes that this service cannot produce an eligible acceptance on either date. There is no authorized exception in this example. The dates are the questioned window, not the next two business days.
Independent sampling of any of the seven historical daily values gives zero on one draw with mass `2/7`. Both draws are zero in `4/49` of paths, so at least one acceptance has toy-model mass `45/49`. This calculation is correct for that sampling model, but the model ignores the known closure. Applying the supplied future calendar instead gives output zero with mass one. Dropping the historical zero days would make the unsuitable iid calculation still more optimistic; it would not create future service.
**Changed condition — open weekdays:** the question instead concerns Monday 30 November and Tuesday 1 December, both supplied as open with the historical weekday regime assumed to continue. A sampler conditioned on the matching weekday selects 2 for each date in this tiny dataset, producing a total of 4. The unconditional iid calculation remains `45/49` for at least one. This difference identifies a consequential model assumption. One observation per weekday does not establish deterministic real-world output or independent calibration; changed demand, staffing, batching or support may make both historical choices unsuitable.
Calendar conditioning also does not preserve every dependency. Consider two eligible two-day historical blocks `[0,0]` and `[2,2]`, equally weighted. Sampling a complete block gives mass `1/2` for at least two acceptances. Sampling the same daily marginal values independently gives `3/4`. If the blocks instead are `[0,2]` and `[0,2]`, the marginal values are unchanged but the whole-block mass becomes one. A narrower or more favorable model result is not evidence that the sampler is correct. Select the sampling unit from the operating conditions and qualify its prediction quality on evidence not already used to choose it.
To check these examples without a separate fixture set, retain the supplied event counts and calendars, enumerate the weighted sample paths, and compare the results with the fractions stated above. Keep three checks separate:
- For a fixed horizon, sum the mass of paths satisfying `K >= k`; for a completion-date question, find each path's first completion date and retain paths unfinished at the horizon. Do not substitute an upper count percentile for a high-confidence minimum count.
- Apply the actual future calendar before interpreting the result. The closed weekend produces zero under the supplied calendar; the open-weekday variant and the two block examples test how changing the sampler changes the conditional calculation.
- Replace one known zero day with unknown observation coverage. The former four-value input is then unsupported; silently removing that day or calling it zero must not pass the evidence check.
These checks establish arithmetic and consistency with the supplied assumptions only. They do not establish agent performance, independent forecast calibration or field effectiveness. Those claims require their own evidence.
## Backtest limitation, costs and reopening
The four-day example has no demonstrated out-of-sample accuracy and is deliberately too small to warrant a service assurance. Its arithmetic can be verified; forecasting adequacy remains unestablished. There is no universal minimum sample size, history length or probability level that repairs an unsuitable population or boundary.
Data repair, repeated forecasts and reviews consume the same capacity used for delivery. Spend that effort where it can change the decision or satisfy a required assurance; reuse a current adequate forecast for unchanged conditions. A new date estimate is not an observation of fulfillment, and a late open item remains in the appropriate overdue population.
Reopen when the required bundle, accepted-result unit, remaining scope, readiness, calendar, staffing/access, work mix, return policy, priority or observed prediction behavior changes. Retain the original forecast and promise so later evaluation can reconstruct what was known and agreed. Uncertainty does not forbid a useful bounded commitment, but its governing terms and authority must establish how that uncertainty is handled.
## Grounds and evaluation limits
OPS.13, by Anatoly Levenchuk, was read in full through MCP FPF Tools at snapshot `20261125T054841Z-7b084255babf17c2`, commit `423f9d3fef92bafec7b092b910e8ce056a0f607d`. Its service and authority conditions remain distinct from the selected Vacanti/Seele forecasting contribution. The event-normalization, exact example and backtest procedure are authored applications; no book case is claimed as independent validation of this draft. FPF attribution follows its [licensing notice](https://github.com/ailev/FPF/blob/423f9d3fef92bafec7b092b910e8ce056a0f607d/LICENSING.md).
Proposed development cases must vary zero versus unknown coverage, a future calendar/regime, aggregate count versus a mandatory bundle, and authority to revise a promise. None has a passing evaluation result attached here.
## Attribution and source scope
Authored AOM text: Anna Lubenchenko, [CC BY 4.0](https://creativecommons.org/licenses/by/4.0/). Source contributions and limits are identified in the [public bibliography](../../bibliography.md). FPF sources are by Anatoly Levenchuk, FPF Library, under CC BY 4.0. This AOM adaptation adds operating instructions, explanations and constructed examples under the stated limits; it does not reproduce or implement every source method.